Tram-train in the Lugano area can proceed after sole appeal is rejected

Switzerland's Federal Supreme Court has rejected the appeal against the Lugano area's tram-train network, confirming that construction work can continue without further legal obstacles. The network will connect Lugano with the Basso Vedeggio and Malcantone areas by 2035.

by Redazione 7 November 2026 2 min read Luganese

On 16 October, the Federal Supreme Court rejected the only appeal filed against the Lugano area's tram-train network. The Ticino cantonal government announced the ruling on Friday. The decision means that construction work, which has already begun, can no longer be halted through legal action.

The appeal had been filed on 11 May 2026 by three private individuals. They asked the Federal Supreme Court to refer the case back to the Federal Administrative Court, the Confederation's appeals body, for further examination of the appellants' property situation. They had also requested a temporary suspension of the start of construction, pending the Federal Supreme Court's ruling on the merits.

The Federal Supreme Court had already issued an initial decision over the summer, choosing not to suspend the construction site. Work was therefore able to begin in recent days, with a ceremony marking the laying of the first stone in Manno, the act that traditionally marks the symbolic start of a construction site. On 16 October, the final ruling arrived, in which the Federal Supreme Court rejected the appeal. As the country's highest judicial instance, no further appeals are possible against this decision. Cantonal authorities now have a definitive legal basis to complete the project.

What the project involves

The Lugano area's tram-train network will connect the centre of Lugano with the Basso Vedeggio and Malcantone areas. The project involves building a rail network that will run along a 12.2-kilometre route. According to current planning, the line is due to enter service in 2035.